Business center “Kyivskyi”

Business center “Kyivskyi”
Contractor

Private client

Location

Kyiv

Service

Construction

Year of completion

2023

Completion period

2 months

Type of construction

Commercial construction

About project

For the facility with a capacity of 230 kW (2nd category of electricity supply), the following works were carried out:

  • Project development;
  • Installation of four 0.4 kV cable lines from the 0.4 kV switchgear of the 10/0.4 kV transformer substation (under construction) to the OPU-1 and VPU-2 of the utility service complex;
  • Installation and commissioning of the electricity metering system and automated control and protection system in accordance with the requirements of DTEK ‘Kyiv Electrical Networks’;
  • Development of the internal power supply system and installation of the protective grounding system.